| REFINERY & PETROCHEMICAL PROJECT EXPERIENCES |
|
|
|
|
|
| No |
Name of
Project |
Project
Owner |
Periode |
Scope of
Work |
| 1. |
Iskandar Muda
Fertilizer Project |
PT.Pupuk
Iskandar Muda ( Persero ) |
1982 - 1984 |
CM |
| |
Capacity : - Ammonia : 1,000 t/day |
Lhokseumawe - North Aceh |
|
|
| |
- Urea :
1,725 t/day |
Indonesia |
|
|
| |
|
|
|
|
| 2. |
Efficiency Analysis of Fertilizer
Plants |
Department of Industry Republic |
1982 - 1984 |
FS |
| |
- P.T. Pupuk Sriwidjaja
(Persero) |
of Indonesia |
|
|
| |
- P.T. Pupuk Kujang
(Persero) |
|
|
|
| |
- P.T. Petrokimia Gresik
(Persero) |
|
|
|
| |
|
|
|
|
| 3* |
Kalimantan Timur – III |
P.T. Pupuk Kalimantan Timur |
1986- 1988 |
E,P,C |
| |
Fertilizer Project |
Bontang -
East Kalimantan |
|
|
| |
Capacity : - NH3 1,000 t/day |
Indonesia |
|
|
| |
- Urea
1,725 t/day |
|
|
|
| |
|
|
|
|
| 4* |
Ammonia Optimization Plant |
Asean Aceh Fertilizer (AAF) |
1987-1988 |
E, |
| |
|
Lhokseumawe - North Aceh |
1988-1989 |
|
| |
|
Sumatera - Indonesia |
|
|
| |
|
|
|
|
| 5. |
Ethylene Glycol Project |
PT. Yasa Ganesha Pura/ |
1989 -1991 |
F |
| |
|
Bank BNI - 1946 , Jakarta - Indonesia |
|
|
| |
|
|
|
|
| 6. |
PUSRI IV Urea Reactor Project |
PT. Pupuk Sriwidjaja (Persero) |
1989 -1989 |
C |
| |
|
Palembang – South Sumatera |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 7 |
Manpower Supply to
USA |
The M.W. Kellogg Overseas |
1989 |
E |
| |
|
Corporation - U S A |
|
|
| |
|
|
|
|
| 8. |
Urea Formal Dehyde Concentrate |
PT. Pupuk Kalimantan Timur |
1989 |
E |
| |
(UFC Project) |
Bontang – East Kalimantan |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 9. |
Polypropelene Project |
Tri Polyta,
Jakarta |
1990 |
E |
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 10. |
Revamping of Ammonia / |
Asean Bintulu Fertilizer (ABF) |
1990 - 1991 |
C |
| |
Urea Fertilizer Plant Project |
Bintulu – Serawak, Malaysia |
|
|
| |
|
|
|
|
| 11* |
PUSRI – IB Fertilizer Project |
PT. Pupuk Sriwidjaja (Persero) |
1990 - 1993 |
E,P,C |
| |
Capacity : - NH3 1,300 t/day |
Palembang - South Sumatera |
|
|
| |
- UREA
1,725 t/day |
Indonesia |
|
|
| |
|
|
|
|
| |
|
|
|
|
| 12. |
Acrylic Fiber Project |
Golden Key Group ( GKG ) |
1991 - 1994 |
PM |
| |
|
Jakarta - Indonesia |
|
|
| |
|
|
|
|
| 13* |
CO2
Preteratment Unit Project AAF |
Asean Aceh Fertilizer (AAF) |
1991 - 1992 |
E,CM |
| |
|
|
|
|
| 14. |
CO2 Pretreatment Unit
Project PIM |
PT. Pupuk Iskandar Muda (Persero) |
|
E, P services |
| |
|
Lhokseumawe – North Aceh |
|
|
| |
|
Sumatera - Indonesia |
|
|
| |
|
|
|
|
| 15* |
Carbon Black Plant
Project |
PT. Cabot Chemical
Jakarta - Indonesia |
1991 - 1992 |
E,P,C |
| |
|
|
|
|
| 16* |
Kaltim I NH3 Optimization |
PT. Pupuk Kalimantan Timur |
1991 - 1993 |
E,P |
| |
Plant |
Bontang - East Kalimantan |
|
CM |
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 17. |
Petronas Lube Oil Blending |
Petronas Penapisan |
1993 - 1994 |
E,P,C |
| |
|
|
|
|
| 18. |
Ammonia Optimization Plant |
PT. Pupuk Iskandar Muda (Persero) |
1992-1993 |
E |
| |
|
Lhokseumawe – North Aceh |
|
|
| |
|
Sumatera - Indonesia |
|
|
| |
|
|
|
|
| 19. |
Ammonia Optimization |
PT. Pupuk Kujang (Persero) |
1992 - 1993 |
E |
| |
Plant |
Cikampek - West Java,
Indonesia |
|
|
| |
|
|
|
|
| 20. |
Methylamine Project |
PT. Langgeng Kinindo Pratama |
1992 - 1993 |
PM |
| |
|
Jakarta - Indonesia |
|
|
| |
|
|
|
|
| 21* |
Melamine Plant Relocation Project |
DSM Kaltim Melamine |
1993 - 1996 |
E,P,C |
| |
|
Bontang - East Kalimantan |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 22* |
Polyethylene Plant |
PT. Chandra Asri Petrochemical |
1993 - 1994 |
E, C |
| |
|
Centre/TEC, Cilegon – West Java |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| |
|
|
|
|
| 23. |
Ammonia Optimization Plant |
PT. Asean Aceh Fertilizer
(AAF) |
1993 - 1994 |
E,P,C |
| |
|
Lhokseumawe – North Aceh |
|
|
| |
|
Sumatera - Indonesia |
|
|
| |
|
|
|
|
| 24. |
Steam System & NG. Line Project |
PT. Asean Aceh Fertilizer
(AAF) |
1993 - 1994 |
E |
| |
|
Lhokseumawe – North Aceh |
|
|
| |
|
Sumatera - Indonesia |
|
|
| |
|
|
|
|
| |
|
|
|
|
| 25* |
Underground Piping Work |
PT. Chandra Asri Petrochemical |
1994 |
C |
| |
CAPC Project |
Centre/TEC, Cilegon – West Java |
|
|
| |
|
Jakarta - Indonesia |
|
|
| |
|
|
|
|
| 26* |
Hexamine Plant Project |
PT. Kaltim Hexamindo Wiratama |
1995 |
C |
| |
|
Jakarta - Indonesia |
|
|
| |
|
|
|
|
| 27. |
Kaltim I NH3 Optimization Plant |
PT. Pupuk Kalimantan Timur |
1995 |
E,P,C |
| |
Project |
Bontang – East Kalimantan |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 28. |
TA-PTA Tank Floor / Lining |
PERTAMINA UP-III Plaju |
1996 |
C |
| |
Repair, Stage I Project |
Palembang – South Sumatera, Indonesia |
|
|
| |
|
|
|
|
| 29 |
TA-PTA Tank Floor / Lining |
PERTAMINA UP-III Plaju |
1997 |
C |
| |
Repair, Stage II
Project |
South Sumatera – Indonesia |
|
|
| |
|
|
|
|
| 30. |
Terminal Facilities |
PT. C.B.I. Indonesia for |
1997 -1998 |
E |
| |
For Olefin Project |
PT. Trans Pacific Petrochemical |
|
|
| |
|
Indotama, Surabaya – East Java, Indonesia |
|
|
| |
|
|
|
|
| 31. |
Musi Pulp Mill Project |
Klockner Stadler Hurter Ltd. For |
1997 - 1998 |
E |
| 31. |
South Sumatera |
PT. Tanjung Enim
Lestari |
|
|
| |
|
Palembang – South Sumatera,
Indonesia |
|
|
| |
|
|
|
|
| 32* |
Vinyl Chloro Monomer
Plant |
PT. Satomo Indovyl Monomer |
1996 - 1997 |
C |
| |
(VCM Plant) Project |
Jakarta - Indonesia |
|
|
| |
|
|
|
|
| 33. |
Piping, & Mechanical Works |
PT. Satomo Indovyl Monomer |
1996 - 1997 |
C |
| |
Of VCM Project |
Jakarta – Indonesia |
|
|
| |
|
|
|
|
| 34* |
Soda Ash Plant Project |
PT. Kaltim Sahid Barito Sodakimia |
1996 - 1997 |
C |
| |
|
Jakarta - Indonesia |
|
|
| |
|
|
|
|
| 35. |
Styrene Butadiene Rubber (SBR) |
PT. Sentra
Sintetikajaya |
1996 -1997 |
C |
| |
Plant. Capacity : 60,000
MTPY |
Jakarta - Indonesia |
|
|
| |
|
|
|
|
| |
|
|
|
|
| 36* |
Styrene Butadiene Rubber (SBR) |
PT. Sentra
Sintetikajaya |
1996 -1997 |
C |
| |
Plant. Capacity : 60,000
MTPY |
Jakarta - Indonesia |
|
|
| |
|
|
|
|
| 37. |
Urea Granule-POPKA |
PT. Pupuk Kalimantan Timur, |
1996 - 1999 |
E,P,C |
| |
(Urea IV Optimization Plant ) |
Bontang – East Kalimantan |
|
|
| |
Capacity : 570,000 MTPY |
Indonesia |
|
|
| |
|
|
|
|
| |
|
|
|
|
| 38. |
NPK Optimization Plant |
PT. Petrokimia Gresik (Persero) |
1998 - 1999 |
E,P,C |
| |
Capacity : 1,000 MT / Day |
Surabaya – East Java |
|
|
| |
Capacity : 1,000 MT / Day |
Indonesia |
|
|
| |
|
|
|
|
| 39. |
Ammonia Plant |
PT. Kaltim Pacific Ammonia |
1997 - 1999 |
E,P,C |
| |
(AMJOS Project) |
Bontang – East Kalimantan |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 40. |
K2 / K3 –Melamine |
DSM Kaltim Melamine |
1998 -1 999 |
E,P,C |
| |
Integration Project |
Bontang – East Kalimantan |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 41. |
H202 (Hidrogen Peroksida) Plant |
PT Asean Aceh Fertilizer
(AAF) |
1998 - 1999 |
C |
| |
Project |
Lhokseumawe – North Aceh |
|
|
| |
|
Sumatera - Indonesia |
|
|
| |
|
|
|
|
| 42. |
Separex Membrane System Project |
PT Asean Aceh Fertilizer
(AAF) |
1998 |
E,C |
| |
|
Lhokseumawe – North Aceh |
|
|
| |
|
Sumatera – Indonesia |
|
|
| |
|
|
|
|
| 43. |
PTA. Turn Around |
PERTAMINA – PTA. Unit Plaju |
1998 |
C |
| |
Maintenance Project |
Palembang – South Sumatera, Indonesia |
|
|
| |
|
|
|
|
| 44. |
Voith Dagang (China) No.1 |
PT. Indah Kiat, Jakarta – Indonesia |
|
E |
| |
Paper Machine Project |
|
1998 |
|
| |
|
|
|
|
| 45. |
Petronas Aromatic Project Piping Work |
Toyo Engineering Corporation for Aromatic Malaysia Sdn. Bhd.
Kerteh, Terengganu - Malaysia |
1998 - 1999 |
C |
| |
|
|
|
|
| 46. |
Ammonia Plant (AMJOS Project) |
PT Kaltim Pacific Ammonia |
1998 - 1999 |
C |
| |
|
Bontang – East kalimantan |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 47. |
Pupuk Iskandar Muda-2 Project |
PT. Pupuk Iskandar Muda (Persero) |
1998 – 2003 |
E,P,C |
| |
(PIM-2 Project) |
Lhokseumawe – North Aceh |
|
|
| |
Capacity : Ammonia 1,200 MTSD |
Sumatera - Indonesia |
|
|
| |
Urea 1,725 MTSD |
|
|
|
| |
|
|
|
|
| 48. |
Civil, Piping, Electrical Engineering Additional Works. |
PT. Tanjung Enim
Lestari |
1999 |
E |
| |
|
Palembang – South Sumatera, Indonesia |
|
|
| |
|
|
|
|
| 49. |
Kaltim-4 Project |
PT. Pupuk Kalimantan Timur |
1999 - 2002 |
E,P,C |
| |
Capacity : Ammonia 1,000 MTPD |
Bontang – East Kalimantan |
|
And |
| |
U r e
a 1,725 MTPD |
Indonesia |
|
Supply |
| |
|
|
|
|
| 50 |
Conveyor Urea Granul |
PT. Pupuk Kalimantan Timur |
1999 - 2000 |
E,P,C |
| |
Popka Project |
Bontang – East Kalimantan |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 51. |
Pembangunan Tanki Ammonia |
PT. Asean Aceh Fertilizer (AAF) |
1999 - 2000 |
E,P,C |
| |
Kapasitas 5000MT NH3 Tank |
Lhokseumawe – North Aceh |
|
|
| |
Project |
Sumatera - Indonesia |
|
|
| |
|
|
|
|
| 52. |
DKM Air Compressor Project |
ABB Lummus Global B.V. |
2000 |
E,P,C |
| |
|
Singapore |
|
|
| |
|
|
|
|
| 53. |
Subcontracting Work for Detailed |
Mitsubishi Heavy Industries (MHI) |
2000 |
E,P |
| |
Engineering and Supply - |
Tokyo - Japan |
|
|
| |
Equipment Project |
|
|
|
| |
|
|
|
|
| 54. |
Betaine & Quarternary Plant - |
PT. Goldschmidt Sumi Asih |
2000 |
Basic Eng’g |
| |
Production Project |
Tambun – Bekasi, |
|
|
| |
|
West Java – Indonesia |
|
|
| |
|
|
|
|
| 55. |
Re-Instrumentasi Kilang |
Pertamina Dumai |
|
|
| |
Pertamina Dumai Project |
Palembang – South Sumatera |
2000 |
E, PM |
| |
|
|
|
|
| |
|
|
|
|
| 56. |
Instrument Technician for Musi Project |
PT. Tanjung Enim Lestari |
2000 – 2001 |
E |
| |
|
Palembang – South Sumatera, Indonesia |
|
|
| |
|
|
|
|
| 57. |
Betaine & Quarternary Plant - |
PT. Goldschmidt Sumi Asih |
2000-2001 |
E,P,C |
| |
Production Project |
Tambun – Bekasi, |
|
|
| |
|
West Java – Indonesia |
|
|
| |
|
|
|
|
| 58. |
Long Kali Palm
Oil Mill Project |
PT.
Perkebunan Nusantara XIII |
|
E.P.C |
| |
|
(Persero) / P.T.P.N. XIII |
2000-2001 |
|
| |
|
Pontianak – West
Kalimantan, Indonesia |
|
|
| |
|
|
|
|
| 59. |
Urea Bulk Storage – 4 Project |
P.T. Pupuk kalimantan Timur |
2001-2002 |
E,P,C |
| |
|
Bontang – East Kalimantan |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 60. |
Design & Engineering Services of |
Mitsubishi Heavy Industries (MHI) |
2001 |
E |
| |
Instrumentation Work Phase II |
Tokyo - Japan |
|
|
| |
Project |
|
|
|
| |
|
|
|
|
| 61. |
Assesment Service for Sugar
Plant Project, Development
Project |
PT. Sumber Madu Bukari |
2001 |
Consultant |
| |
|
Gedung Lina, Jl.HR.Rasuna Said |
|
|
| |
|
Jakarta - Indonesia |
|
|
| |
|
|
|
|
| 62. |
Rehabilitation and Operation |
PT. Petrokimia Gresik
(Persero) |
2001 |
E.P.C. |
| |
Flexibility of Superphospate Plant |
Gresik – Surabaya, East Java |
|
|
| |
Project |
Indonesia |
|
|
| |
|
|
|
|
| 63. |
Materials Supply – MHI Japan |
Mitsubishi Heavy Industries (MHI) |
2001 |
Materials |
| |
Project |
Tokyo - Japan |
|
Supply |
| |
|
|
|
|
| 64. |
Supply Desalination Unit-3 |
P.T. Pupuk Kalimantan Timur |
2001 |
E.P.C. |
| |
Project |
Bontang – East Kalimantan |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 65. |
Site Preparation for New Plant |
PT. Goldschmidt Sumi Asih |
2001 |
Site |
| |
Quarternary Product Project |
Tambun – Bekasi |
|
Preparation |
| |
|
West Java – Indonesia |
|
|
| |
|
|
|
|
| 66. |
A B I / 00403 (Modification – |
Pertamina Unit Pengolahan – V |
|
E,P,C |
| |
Coloumn HVU.III) Project |
Balikpapan - Indonesia |
2001 |
|
| |
|
|
|
|
| |
|
|
|
|
| 67. |
Granulation Steel Structure |
Mitsubishi Heavy Industry (MHI) |
2001 - 2002 |
Supply |
| |
Project |
Tokyo - Japan |
|
|
| |
|
|
|
|
| 68. |
Supply Of Pipe Materials |
PT. Petrokimia Gresik (Persero) |
2001-2002 |
Supply |
| |
Project |
Gresik – Surabaya, East Java |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 69. |
Engineering and Design Service |
VICO INDONESIA |
2001-2002 |
E |
| |
for Various Project No.05850 |
Jakarta - Indonesia |
|
|
| |
|
|
|
|
| 70. |
Pembuatan Tanki Ammonia |
PT. Petrokimia Gresik (Persero) |
2002 |
E.P.C. |
| |
Kapasitas 7.500 MT Single |
Gresik - Surabaya |
|
|
| |
Wall Project |
East Java - Indonesia |
|
|
| |
|
|
|
|
| 71. |
Jasa Verifikasi Teknis dan Manajemen |
PT. Batavindo Krida Nusa |
2002 |
PM |
| |
Proyek Pembangunan |
Jakarta - Indonesia |
|
|
| |
Pabrik Epoxy Resin |
|
|
|
| |
|
|
|
|
| 72 |
Study Of BOG Treatment Project |
PT. Asahimas Chemical |
2002 |
F |
| |
|
Anyer – Serang, Province
Banten |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 73. |
Re-Alignment Bonna KPA |
PT. Kaltim Pasifik Amoniak |
2002 |
C |
| |
Project |
Bontang, East Kalimantan |
|
|
| |
|
Indonesia |
|
|
| |
|
|
|
|
| 74. |
Jasa Engineering 124-C Project |
PT. Petrokimia Gresik (Persero) |
2002 |
E |
| |
|
Gresik – Surabaya |
|
|
| |
|
East Java – Indonesia |
|
|
| |
|
|
|
|
| 75. |
Rimba Belian Palm
Oil Mill Project |
PT. Perkebunan Nusantara
XIII |
2002-2003 |
E.P.C. |
| |
|
(Persero) / P.T.P.N. XIII |
|
|
| |
|
Pontianak – West Kalimantan, Indonesia |
|
|
| |
|
|
|
|
| 76. |
Supply Vehicle Tester Equipment |
PT. Kharisma Alam Sakti Utama |
2002 |
Supply |
| |
Project |
Jakarta – Indonesia |
|
|
| |
|
|
|
|
| 77. |
Exxon Drafting Services Project |
PT. Exxon Mobil Cepu |
2003 |
E |
| |
|
Jakarta – Indonesia |
|
|
| |
|
|
|
|
| 78. |
Construction Inspection Support |
Vico Indonesia, Jakarta –
Indonesia |
|
E |
| |
Services Project |
|
2003 |
|
| |
|
|
|
|
| 79. |
Installation of Nilam VLP Gas |
Vico Indonesia, Jakarta - Indonesia |
2004 |
P.C. |
| |
Compression Project Tender
No. 14120 |
|
|
|
| |
|
|
|
|
| 80. |
Kujang – IB Project |
PT. Pupuk Kujang |
2003-2005 |
E.P.C. |
| |
Capasity : - NH3 1,000
t / day |
Cikampek - West Java |
|
and |
| |
-
Urea 1,725 t / day |
Indonesia |
|
Supply |
| |
|
|
|
|
| 81. |
N.P.K. Fertilizer Malaysia Project |
NAFAS Bajakimia SDN.
BHD. |
2003-2004 |
E.P.C. |
| |
Capasity : 917 MT / Day |
Malaysia |
|
|
| |
|
|
|
|
| 82. |
Ammonia Tank |
PT. Sentana Adidaya Pratama |
2004-2005 |
E.P.C.Com. |
| |
Capasity : 7,500 MT Double Wall |
Medan |
|
|
| |
Project |
North Sumatera - Indonesia |
|
|
| |
|
|
|
|
| 83. |
Technical and Cost Estimation |
PT. Styrindo Mono Indonesia |
2005 |
E |
| |
Study of Ethylene Tank T-2 BOG |
Jakarta - Indonesia |
|
|
| |
Recovery System and Reduce |
|
|
|
| |
Ethylene Working Level in FB-901 |
|
|
|
| |
|
|
|
|
| 84 |
Balongan BlueSky Project |
PT
Pertamina ( Persero ) Direktorat Hilir |
2002-
2005 |
E. P. C |
| |
|
Manajemen Proyek
Hilir Pengolahan |
|
|
| |
|
|
|
|
| 85. |
Bonna Pipe
Stabilization Project |
PT Kaltim Pacific
Amoniak |
2004 – 2006 |
E.P.C |
| |
|
|
|
|
| 86. |
Bioethanol
Plant for Gasohol Project |
PT Medco Ethanol
Lampung |
2006 – 2007 |
E.P.C |
| |
|
|
|
|
| 87. |
Modernisasi LOBP UPP Surabaya Project |
PT Pertamina ( Persero
) |
2007 – Present |
E.P.C |
| |
|
|
|
|
| 88. |
Cilacap Crude Tank Floating Roof Type |
PT Pertamina ( Persero ) UP IV Cilacap |
2007 – Present |
E.P.C |
| |
|
|
|
|
| 89. |
Biodiesel
Plant Project |
PT Bakrie Rekin Bio Energy |
2007 – 2008 |
E.P.C |
| |
|
|
|
|
| 90. |
RCC Revamping II Pertamina Balongan |
PT Pertamina ( Persero ) |
2007 – Present |
E.P.C |
| |
|
|
|
|
| 91. |
Biodiesel Wilmar 2 & 3, South Sumatera |
PT
Wilmar, Sentana |
2007 – 2008 |
C |
| |
|
|
|
|
| 92. |
LPG Lembak, South
Sumatera |
PT Surya Esa Perkasa |
2006 – 2007 |
E.P.C |
| |
|
|
|
|
| 93. |
RCC of Gas to Propylene Project (ROPP) |
PT Pertamina ( Persero ) |
2008 – 2010 |
E.P.C |
| |
|
|
|
|
| 94. |
Ammonium Nitrate Orica Project at Bontang, Kalimantab |
PT Kaltim Nitrate Industri ( ORICA ) |
2008 – Present |
E.P.C |
| |
(Phase Site
Preparation Reclamation) |
|
|
|
| |
|
|
|
|
| 95. |
Maintenance Bone & Takalar Sugar Plant, Makassar |
PT Perkebunan Nusantara XIV |
2008
– Present |
E.P.C |
|
|
|
|
|