Rekind Builds Tonasa Steam-Generated Power Plant
News Category : Corporate News
Rekind, as represented by Mr. Ali Suharsono, together with Mr. T. Mazaki, representing Kawasaki Heavy Industries (KHI), and Mr. Sattar Taba, President Director of PT Semen Tonasa, in his capacity as project owner, signed a contract for the construction of the Tonasa Coal-Fired Power Plant Project (TCFPP), 2 x 35 MW capacity, on Monday,31 May 2010. The event was held at the office of the Indonesian Cement Association at Graha Irama Building, Jakarta. Also present on the occasion were representatives from the Board of Commissioners of PT Semen Tonasa, Mr. Taslim Arifin, and from Rekind, Mr. Setyo Aryono Prabowo.
The TFCPP project is located in the Regency of Pangkep, South Sulawesi, with a total development period of 27.5 months beginning in June 2010. For the umpteenth time, Semen Tonasa has entrusted the EPCC scope of work of its project construction to Rekind, who acts in consortium with KHI. The final result of this TFCPP project is expected to meet the electricity needs of Semen Tonasa's fifth project.
Mr. Radian Hozen, as Project Director, leads the project team, with Mr. Dudi Agung serving as Project Manager. The project team is currently doing the initial preparations in relation with a contract between the two parties. Let us pray for support the implementation of this project so that it can be completed on time and with high quality.
|
|
|
|